Walls going up on Fernie's new fire hall
The main structure should be done by December. Crews move in late next year.
By The Kootenay Dispatch newsroom

Fernie's new fire hall is starting to look like a building. Crews spent the first half of November setting precast concrete wall panels, the city says. The main structure should be finished in December, and work on the inside floors starts in the new year.
Water, sewer, power and communications lines reached the site in October. The foundation is poured and the footprint has been backfilled.
Fernie Fire Rescue works out of a temporary hall for now. The city says that space does not meet the needs of a modern department.
The new hall is being built on part of Prentice Park. The project budget is $16 million. A $7 million provincial and federal grant covers about 45 per cent of construction.
Crews are expected to move in late in 2027.